Timeline
| Week | Date | Stage | Tasks | Deliverables |
|---|---|---|---|---|
1. |
Sept 20-4 |
Planning | Meet with sponsor - Jeff's answers, meeting notes Write project proposal: description - Tammy; scope - Mariela; the rest - Rachael |
Proposal |
2. |
Sept 27-1 | Analysis |
User/task Matrix - Rachael |
User/task Matrix |
3. |
Oct 4-8 | Analysis | Do an inventory of |
Content Inventory |
4. |
Oct 11-15 | Design | Work individually on sitemaps. Meet to consolidate versions of sitemaps. |
Old Sitemap New Sitemap |
5. |
Oct 18-22 | Design | Individual work on content areas: |
|
6. |
Oct 25-29 | Design | Group meeting to discuss content, wireframes, and work on labels that emerge from individual work so far. Continue individual work on content areas to create page layouts. Meet with client to discuss content, wireframes & design. |
Labels & Naming Rules |
7. |
Nov 1-5 | Construction | Finalize graphic design - Alex. |
Design Standards |
8. |
Nov 8-12 | Construction | Implementation of front page - Alex. Content management - Tammy. Intranet coding - Rachael. Public site coding - Mariela. |
FASTRAC Website |
9. |
Nov 15-19 | Verification | Demonstration meeting with clients. Training session with clients. Continue construction tasks. |
|
10. |
Nov 22-26 | Verification | Master list for public site - Tammy. |
|
11. |
Nov 30 | Final Presentation |